Cost & Financial Visibility

Synced with Foundation Software — Real-time job cost data

Foundation ConnectedLast sync: May 10, 8:00 AM38 cost records across 3 jobs10 change orders tracked

Contract Value

$4.61M

3 active jobs

Revised Budget

$4.37M

incl. change orders

Actual Cost

$3.94M

90% of budget

Gross Profit

$110K

2.4% margin

Billed to Date

$3.99M

86% of contract

Retention Held

$399K

10% retention

Budget vs Actual vs EAC

Per-project cost comparison from Foundation

Meridian Tower - L...Legacy Medical Cen...Grand Hyatt Renova...$0.0M$0.6M$1.1M$1.6M$2.2M
  • Revised Budget
  • Actual Cost
  • Est. at Completion
Cost Type Breakdown

Actual costs by category

Labor
$1.27M
Material
$2.67M
Total$3.94M
Gross Profit & Margin by Project

Projected gross profit and profit fade/gain

Meridian Tower - L...Legacy Medical Cen...Grand Hyatt Renova...$-70K$-35K$0$35K$70K
  • Gross Profit
  • Profit Fade
Job Financial Summary — Foundation Data
JobContractRev. BudgetActualEACVarianceCompleteGross ProfitMarginFade

Meridian Tower - Levels 3-8

2026-001

$1.33M$1.23M$1.11M$1.27M$-33K
90%
$66K5%$-33K

Legacy Medical Center

2026-002

$1.15M$1.05M$944K$1.08M$-35K
90%
$68K5.9%$-33K

Grand Hyatt Renovation

2026-003

$2.13M$2.09M$1.88M$2.15M$-63K
90%
$-24K-1.1%$-63K
Total$4.61M$4.37M$3.94M$4.50M$-131K$110K2.4%$-128K
Foundation Sync Log
May 10, 8:00 AMFoundation sync completed — 36 job cost records updated
May 10, 8:00 AMBilling data refreshed for 3 active jobs
May 10, 8:00 AMCash flow data updated through May 2026
May 10, 8:00 AM10 change orders synced (7 approved, 3 pending)
May 10, 7:00 AMScheduled sync completed — no new data
May 9, 8:00 PMFoundation sync completed — 2 new cost entries
May 9, 8:00 AMJob 2026-001 cost code 09 30 13.02 over budget by $5,800
May 8, 8:00 AMFoundation sync completed — 36 job cost records updated