Production Tracking
Real-time field production monitoring with GPS-tagged photo documentation
Today's Installation
6,840 SF
+12% vs target
Weekly Total
28,400 SF
On pace
Avg Rate (All Projects)
306 SF/day
-5% vs estimate
Production Photos
42
34 GPS tagged this week
Weekly Production Trend (All Projects Combined)
- Actual SF
- Planned SF
Production Rate: Actual vs Estimated (SF/Day per Crew)
- Actual Rate
- Estimated Rate
Project Production Summary
Meridian Tower - Levels 3-8
Porcelain Tile
-5%
Completed
89,900 SF
Remaining
55,100 SF
Daily Rate
285 SF/day
Days to Complete
194 days
Legacy Medical Center
Epoxy Terrazzo
-18%
Completed
36,080 SF
Remaining
51,920 SF
Daily Rate
180 SF/day
Days to Complete
289 days
Riverside Corporate Campus
LVT / Carpet Tile
+8%
Completed
87,360 SF
Remaining
24,640 SF
Daily Rate
520 SF/day
Days to Complete
48 days
Grand Hyatt Renovation
Ceramic Tile / Natural Stone
-30%
Completed
68,250 SF
Remaining
126,750 SF
Daily Rate
195 SF/day
Days to Complete
650 days
Oakwood Elementary School
Epoxy Coating
+3%
Completed
23,100 SF
Remaining
18,900 SF
Daily Rate
350 SF/day
Days to Complete
54 days